Monday 8th September

Steady progress has been made with construction through August.  The brickwork and blockwork has been completed and the roof timberwork is substantially completed.

Carpentry

The floor joists and flooring over the changing rooms have been completed.  The roof timber frame has been completed with the exception of the corners, where the steel hip rafters are on site and due to be erected this week.

Brickwork and blockwork

The external cavity wall has been completed.  Internally all the the load-bearing blockwork walls and the internal partition walls that are not load-bearing have been completed.