Saturday 2nd November

With the shutters down the clubhouse shell (construction phase 1) looks essentially complete.

Windows and Doors

Behind the shutters the front door and french windows still have not been delivered so the shell is not quite complete.  The contractor hopes these will be delivered later in November when he will undertake final snagging prior to handing the building over to the Club.

Fencing and Security

Whilst we are waiting for handover the Club has been active on Saturday mornings erecting the permanent fence around the west side of the building and trimming the soil to form a stable slope.  Once that is complete we will be installing CCTV.

Opening

We plan to hold a formal opening in the spring when the weather is more likely to be pleasant.  That also gives the Club time to lay temporary paths between the building and the gates and time to fit out the boat store.